Mohmand Dam cost jumps 115%
The Express Tribune • • 1 min read

The Express Tribune reported that Wapda has put the revised cost of the under-construction Mohmand Dam at Rs666 billion, up Rs356 billion, or 115%, from the Rs310 billion approved in 2018. The updated estimate was presented to the Central Development Working Party this week, but the body did not decide on it because of limited time.
Officials attributed 51% of the increase to dollar parity, while project explanations also cited design changes, the 2022 floods and security issues among factors behind higher costs and delays. About 57% of physical work was complete as of last month, with Rs275 billion spent; the original completion target was September 2025. The revised estimate puts the dam component at Rs267 billion and power generation at Rs399 billion, while the project is expected to add 2.9 billion units to the national grid and provide drinking water to Peshawar.
At a glance
- Wapda’s revised Mohmand Dam estimate is Rs666 billion, 115% above the 2018 approval.
- About 57% of physical work was complete last month, with Rs275 billion spent.
- The project is expected to add 2.9 billion units to the national grid.
Originally reported by The Express Tribune
This page is Investify's own summary. The full report, with all details and context, is on the publisher's site.
Read the full storyWant the full article here?
Log in to read the full article in the Investify reader, in English or Urdu.
Investify summarizes Pakistan Stock Exchange news in its own words and links each story to its original publisher. We always credit the source so you can read the full report and verify the details before making financial decisions.
More PSX market news
Soya Supreme maker APAG expands into mayonnaise, saucesProfit• 18 Nov 2026
Pakistan seeks wider access to Singapore’s food market, deeper fintech tiesProfit• 18 Nov 2026
SBP revises financing rules for builders, developersMettis• 18 Nov 2026
SBP revises guidelines for builders, developers financingMettis• 18 Nov 2026
Govt, APTMA discuss export finance facilities, textile competitivenessMettis• 18 Nov 2026
Bank deposit rate edges up 1bps in OctoberMettis• 18 Nov 2026