Project Status Of 36.50 Hybrid Power Project Of Mughal Energy Limited (Subsidiary Company)
Operations UpdateMughal Energy Limited has successfully achieved key milestones in the development of its 36.50 MW Hybrid Power Plant, with controlled cooling down processes and final testing underway.
Key Findings
- Steam blowing of the boiler and main steam lines has been successfully completed.
- The plant is undergoing final testing and safety measures.
- Commercial billing is expected to commence within March 2026.
⚡
Highlights summarize the key points from the company's official PSX filing. View the original filing for the complete details before making financial decisions.