At-Tahur commences first 500 kW biogas generator and plans 4 MW project
Operations UpdateAt-Tahur Limited, in partnership with White Clover Energy (Pvt.) Limited, has commenced its first 500 kW biogas generator. The company says it plans to bring 4 MW online in stages over approximately 12 months, with 1.5 MW expected by or before December 31, 2026, and anticipates a positive financial impact.
Key Findings
- The first 500 kW biogas generator has commenced operations.
- At-Tahur is partnering with White Clover Energy (Pvt.) Limited on the project.
- The project has a planned capacity of 4 MW, intended to come online in stages over approximately 12 months.
- The company expects 1.5 MW to come online by or before December 31, 2026.
- The company states that the project will have a very large positive financial impact.
Disclosure Details
Expected Completion Date
31/12/2026
Entities Involved
At-Tahur Limited, White Clover Energy (Pvt.) Limited
Impact
The company expects a very large positive financial impact from the biogas power generation project.
⚡
Highlights summarize the key points from the company's official PSX filing. View the original filing for the complete details before making financial decisions.