EnergyQuick read

Stakeholders blamed for Tarbela-5 cofferdam collapse

Dawn • • 1 min read

Stakeholders blamed for Tarbela-5 cofferdam collapse

Dawn reported that a government-formed inquiry panel has held the contractor, the consultant and the employer, Wapda, responsible for the cofferdam collapse at the 1,530MW Tarbela-5 Extension Hydropower Project. Among the main reasons cited were design changes made after the contract was signed, which the panel said were not authorised. It also found that the employer approved the altered design late in construction without checking whether the change was permitted under the contract.

The collapse has delayed the project by at least two years and pushed costs up more than 285 per cent, with the budget rising from Rs82 billion to Rs317bn. The Planning Commission said the levelised generation cost over 30 years could reach roughly Rs27 to Rs28 per unit, a record for renewable energy in the country. The commission judged the project economically unworkable as a result.

The panel also noted that a weaker rock-filled cofferdam design was adopted across the whole project at the contractor's request. The consultant forwarded a request for a performance report to the contractor rather than reviewing it independently, and the reply came more than a year later. Completion is now targeted for end of June 2028 instead of 2026, and the project is funded partly by $700m in loans from the World Bank and the Asian Infrastructure Investment Bank.

At a glance

  • Inquiry panel holds contractor, consultant and Wapda responsible for the cofferdam collapse.
  • Project cost has risen from Rs82.36bn to Rs317bn and completion now targets end of June 2028.
  • Report says an unapproved design change to a weaker cofferdam was among the main causes.
Sectors:Power Generation & Distribution

Originally reported by Dawn

This page is Investify's own summary. The full report, with all details and context, is on the publisher's site.

Read the full story

Want the full article here?

Log in to read the full article in the Investify reader, in English or Urdu.

Investify summarizes Pakistan Stock Exchange news in its own words and links each story to its original publisher. We always credit the source so you can read the full report and verify the details before making financial decisions.

Built for PSX investors

Business news.Every filing, summarised.

Top stories from Pakistan's business press and key findings from every PSX announcement.

Investify announcement summary with key findings from a PSX filing
Investify app home screen with Pakistan business news and PSX filings