FCC clears hurdles to completion of Nai Gaj Dam
Dawn • • 1 min read

Dawn reported that the Federal Constitutional Court (FCC) has annulled several Sindh High Court rulings in the protracted Nai Gaj Dam case. The court also instructed the contractor to finish outstanding work in line with the original agreement, the arbitral verdict and a memorandum of understanding dated Sept 21, 2021. Those earlier SHC decisions had permitted NEIE SMADB-LILLEY-RMS Karachi to seek cost increases above the agreed conditions.
A two-judge bench led by Chief Justice Aminuddin Khan said it expected every party, including Wapda, to honour its commitments. No court may intervene before the dam is finished, except through the dispute resolution route in the original contract. The 21-page judgement says the aim is to stop litigation delaying an important public infrastructure project.
Wapda must decide within 15 days of receiving any application from the contractor that clearly commits to resuming work under the original terms. It will set a reasonable time extension under the contract rules, but that extension brings no further price escalation, compensation or financial gain beyond what was already settled. If the contractor misses that deadline or refuses to finish the work as the contract requires, Wapda may re-tender the remaining work at the contractor's risk and cost. The dam, on the Gaj River in Dadu district, is designed to bring nearly 28,800 acres under cultivation and yield about 4.2MW of hydropower.
At a glance
- The FCC set aside several Sindh High Court orders in the Nai Gaj Dam dispute.
- The contractor must complete remaining work under the original contract, arbitral award and MoU.
- An extension of time granted to the contractor will not allow any further price escalation.
Originally reported by Dawn
This page is Investify's own summary. The full report, with all details and context, is on the publisher's site.
Read the full storyWant the full article here?
Log in to read the full article in the Investify reader, in English or Urdu.
Investify summarizes Pakistan Stock Exchange news in its own words and links each story to its original publisher. We always credit the source so you can read the full report and verify the details before making financial decisions.
More PSX market news
NEPRA questions tariff revision requests for three solar power projects over potential financial burden on consumersProfit• 25 Nov 2026
Pakistan secures 25,000-tonne tuna quota with $200 million export potential, invites Maldivian investment in canning industryProfit• 25 Nov 2026
Pakistan invites European, Chinese businesses to establish JVs in agri, food processing sectors, seeks long-term sourcing deals with MalaysiaProfit• 25 Nov 2026
PSX pares early gains as global sell-off weighs on sentimentTribune• 25 Nov 2026
Hinopak Motors H1 profit edges up 5% to Rs567mMettis• 25 Nov 2026
Pakistan, China agree on government-to-government arrangements for fuel storage, terminal facilitiesDawn• 25 Nov 2026