Pakistan's only coal conveyor system at Port Qasim non-functional since Nov 18, disrupting coal imports
Dawn • • 1 min read

Pakistan International Bulk Terminal’s coal conveyor at Port Qasim has been out of service since Nov 18, slowing coal imports for power plants and industries, Dawn reported. Manual unloading has cut the terminal’s discharge pace to 3,000 tonnes a day from its usual 30,000, while repairs could take eight to 10 days.
Jamshoro Power Company says five vessels waiting to unload could incur more than $2-3 million in demurrage, and warned that inadequate coal stocks could mean capacity payment losses of about Rs2.2 billion per month. PIBT has declined requests to declare force majeure, saying unloading continues by conventional methods; delayed cargoes could also raise coal procurement and electricity-generation costs.
At a glance
- Coal discharge has fallen to 3,000 tonnes per day from 30,000.
- Jamshoro Power Company cited potential monthly capacity payment losses of Rs2.2 billion.
Originally reported by Dawn
This page is Investify's own summary. The full report, with all details and context, is on the publisher's site.
Read the full storyWant the full article here?
Log in to read the full article in the Investify reader, in English or Urdu.
Investify summarizes Pakistan Stock Exchange news in its own words and links each story to its original publisher. We always credit the source so you can read the full report and verify the details before making financial decisions.
More PSX market news
Gold price in Pakistan for today, November 23, 2026Profit• 23 Nov 2026
Silver price in Pakistan for today, November 23, 2026Profit• 23 Nov 2026
Missed the boat? Pakistan may need a plan B for economic growthDawn• 23 Nov 2026
India's Tata Steel to buy 26.4% of APL Apollo for $1.67 billionBR• 23 Nov 2026
AI rout deepens, keeping Indian rupee rally alive on foreign equity buyingBR• 23 Nov 2026
Australia shares set to slide at open, NZ fallsBR• 23 Nov 2026